|
Details
of bridge project
explored by participants
in online forum
Impact
on historic properties
among highlights of chat
By
Konnie McCollum
Staff Writer
 |
(July 2009) As a way to continue to encourage public
input into the Milton-Madison Bridge Project, officials held an online
forum June 2 at the projects website, www.MiltonMadisonBridge.com.
During two different sessions, community representatives from the Project
Advisory Group, residents of the surrounding community, historic property
owners and historic interest representatives had an opportunity to ask
project team members extensive questions about the three-year, $5 million
environmental study to build a new bridge across the Ohio River.
Involving the public in the process is part of the requirements for the
National Environmental Policy Act, which should be completed by mid-June
2010, according to Tim Sorenson, of lead consulting firm Wilbur, Smith
Associates. Once NEPA documents are finalized, the next stage is final
design, right-of-way acquisition, utility relocation and any permitting,
which generally takes between two to four years, according to project
team members during the chat.
We have received great input from the public to this point. We have
been able to use public input to shape the location alternatives as well
as the bridge aesthetics, team members stated during the online
chat.
The Canip Creek alternative has been driven very heavily by input
through our public involvement process. What has been greatly appreciated
is the continued input from the local officials and the PAG members to
help keep this project on track.
Questions varied during the two, two-hour sessions, including what a realistic
cost would be for such a project, and how much funding is already put
aside. According to project team members, a good cost estimate for a bridge
project of this type would be $100-$200 million. The Indiana Department
of Transportation has $10 million set aside in their funding plan for
the project, while the Kentucky Transportation Cabinet has about $40 million
shown in the last four years of the new six-year highway plan. That funding
would still have to be approved by the Kentucky Legislature early in 2010.
The poor condition of the bridge was also discussed. The comment was made
that rumors have swirled that there is not a chance a new bridge could
be under construction before 2020, or even 2017 at the very earliest.
The question was posed: Are those realistic dates or is there
a possibility we could see construction begin much earlier?
Team members responded with, because the existing bridge is in poor
condition, the project team has made an effort to expedite the process
with sensitivity to the historic communities. We hope that our earlier
than normal coordination with the Section 106 parties has created good
working relationships.
According to the Citizens Guide of the
Advisory Council of Historic Preservation, Section 106 of the National
Historic Preservation Act of 1966 requires the federal agencies involved
in a project to take into account the effects of their undertakings on
properties listed or eligible for listing in the National Register and
to give the Advisory Council on Historic Preservation a reasonable opportunity
to comment.
Consulting parties include state historic preservation officers, Native
American tribes, local governments and individuals or organizations with
a demonstrated interest in the project.
Section 106 review does not mandate preservation because sometimes there
is no way for a needed project to proceed without harming historic properties.
It does, however, ensure that preservation values are factored into the
planning and decision processes.
The point of 106 reviews is not to stop projects, but to ensure that federal
agencies fully consider historic preservation issues and the views of
the public during project planning.
That point was questioned at the April PAG meeting, which was held at
the Livery Stable in Madison, Ind. One of the local rumors is that
the Section 106 parties can stop any project. Is this true? asked
PAG member Peter Woodburn.
John Carr, the project manager, said it is not true. However, the
Section 106 opinions are held in high regard and there are laws that we
will address on this project, he said. We would like the parties
to sit down with us and help us review resources as we consider alignments
within alternatives.
A comment then arose that a letter from the National Trust for Historic
Preservation, signed by several organizations involved with the 106 process
on the bridge project, was read at the March PAG meeting. That letter
gave a preferred alternative and specifically did not recommend the superstructure
replacement alternative, one of the four remaining alternatives for the
project. Several 106 parties signed the letter, but not all of them agree
with it.
Given the tremendous detrimental impact of having no bridge in this
community, it appears that the letter does not address the local sentiment,
said attorney Nathaniel Adams, a PAG member representing historical interests
in Milton. The PAG, public and team that have worked so hard on
this project should not be subject to the narrow view handed down by the
National Trust.
Does this organization have the right to stop the project,
another PAG member asked.
Carr said neither the National Trust nor the Section 106 Consulting Parties
can stop the project. The decision rests with the states of Kentucky and
Indiana and the Federal Highway Administration on what they wish to do
with the bridge.
The National Trust has issued an opinion. We are respectful of that
opinion and we have recorded it, he said. Once we have all
the information on the existing piers and the more detailed studies, a
more informed decision can be made about this option.
Another PAG Member, attorney Nathaniel Adams,
During the online chat, Link Ludington, an Indiana Department of Natural
Resources historic sites architectural historian, asked In
the event that building on the existing piers is ruled out, would evaluation
of any proposal for possible re-use of the old bridge by another entity
likely be a direct result of the Section 106 process?
Team members said this would typically be a condition of a Memorandum
of Agreement, part of the 106 process. Any proposals for taking over the
bridge would be considered by KYTC after the 106 process has been completed.
Although an initial Section 106 meeting was held in February for the bridge
project, another one is not scheduled until mid-summer when the Area of
Potential Effect, has been narrowed, said Sorenson.
Officials have involved us in the process so far, said John
Stacier of Historic Madison Inc., one of the organizations involved in
the 106 process. We certainly hope to be involved further as the
project develops.
|